What is Happening at the Union?
Updates to Illini Union Projects
The Illini Union has several ongoing projects taking place over the next few years. This is a place where we will provide periodic updates for those projects, so our customers and university community can stay apprised of what is happening.
Illini Union Roof Project - 2024-2026
The replacement project will take approximately two years with a projected completion date in late 2026.
The Illini Union will be operational throughout the construction. The below notes indicate closures and changes as needed:
CURRENT HAPPENINGS/TIMELINE:
this schedule is subject to change
All scaffolding and overhead protection has been removed.
- All sidewalks, entrances, circle drive, lot D-10, and lot D-11 to the Illini Union North Building as well as the dock are open.
- The sidewalks approaching the Illini Union, remain open throughout the project.
- All construction and scaffolding is fenced with restricted access to construction staff only.
- Phase 1 (North): COMPLETE
- Scaffolding has been removed from the north and east sides of the Union.
- Phase 2 (South): July 2025-current - COMPLETE
- All south side fourth floor hotel rooms are open.
- Patio furniture will return during Spring Break in March 2027.
- Roofing Phase 3 (Center): March 2026-current - in progress
ACCESS CLOSURES
Current
- The West Patio, entry doors, Diana Fountain, and all sidewalks leading to the west side of the Illini Union will be closed to both staff and the public except for emergency egress from the building.
Floor Updates
- The north 3rd floor is currently being re-painted. All offices and rooms are open and accessible.
- New wayfinding building maps have been installed on the first floor, second floor (north), and Underground.
- The East & West Hallways were re-painted with a new Illinois blue spirit inspiration, along with new digital sign systems being installed in the SW entrance, outside the Illini Rooms, in the Courtyard Cafe, and in the NW hallway.
- The SW and SE entry ways have been repainted with new graphics in the stairwell leading to the Underground.
McKinely Clinic/Reflection Space
In the Illini Union Underground, where CLASS was located, a remodel is happening turning the space into a McKinley Convenience Care Clinic on the right side and a Reflection, Meditation & Sensory Room on the left side. This process is in the demolation/preparation phase. Completion is targeted for early 2027.
- Illini Union will close at 8pm on Monday, November 23 as water will be shut off for construction tie-ins. It will reopen on Tuesday, November 24 at 7am.
Illini Union Elevator Modernization
The elevators in the Illini Union will be receiving required modernization upgrades. The elevators will be taken off line one at a time for the work. One of the two elevators on each end (north and south) will be operational during these times. There may be a few times when both are unavailable, but we will alert you ahead of time.
TIMELINE:
North End - July 7, 2026-December 12, 2026
- E2 will be unavailable from July 7-Dec. 12, 2026. E1 will be operational during this time.
South End - November 2026-March 25, 2027
- E5 is unavailable currently. E6 is still operational to access south 2nd floor and Hotel floors.